Hi,
I’m having an issue in a project, where the tasks are not being grouped by the level they have assigned in the Link field.
Any ideas what might be causing the issue.
Thank you!!
Hi,
I’m having an issue in a project, where the tasks are not being grouped by the level they have assigned in the Link field.
Any ideas what might be causing the issue.
Thank you!!
Check your Grouping settings?
Duh, you are right. It never ocurred to me that was the issue.
Thank you
Also double check if someone else may have changed the grouping settings and saved the page. If it’s a project page, they are all shared. It can be common fir people to adjust and save without knowing this