How do you set the project end date? I have the phases set to September to June but my flow gen schedule ends in December.
Also, the calendar exceptions list dates outside of the project range - is here a way to remove these - mine go back to 2013?
Select the project in the schedule view (Gantt) and in the “controls” tab, add or set a “finish-no-later-than” (FNLT) constraint to your desired project end date. See Help
There is not currently. But, I can see that being useful.
1 Like
Thank you - I thought I’d done that but maybe I hadn’t hit generate