Completion percentage on pipeline steps

Hi,

I would like to change what status the completion percentage on top of pipeline steps refers to.

step_percentage

This percentage correspond to tasks whose status is final, and I would like to apply it to another one. While edition the field, I can’t see anything that would allow it.

Is this possible?
And if it is, can it set to different statuses for different steps, or would it be the same status for all steps?

Many thanks.

Hi,

I figured out how to do it.

Right click Status Task under the step name, then Summary, Percentage, and select the status you would like to display the percentage for.

The Show Details Only and Show Page (Columns) Summary options (squared in red on the screenshot) need to be checked.